Projects
The Port Authority's projects include capital projects on our Aerospace Center campus. Stop back often for an update or join
our e-mail list to receive regular updates on key projects via our electronic newsletter.
|
The Port Authority has overseen more than $10 million in capital improvements projects in the past two years.
UPDATED December 28, 2011
Building Demolition
DESIGN PHASE
Currently anticipated to occur in 2012, this project will include the demolition of five out-buildings and the water tower. Final project schedule is dependant upon completion of the fire pump relocation and waterline consolidation projects.
Sidewalk/Walkway Updates
COMPLETE
Layton Excavating Has completed a series of on-site sidewalk and walkway updates, including an extension of the on-site walking path on the East side to meet up with the Heath recreational trails, a rear access to the UPS building northeast of Building 4, addition of a recessed access to the Upper Parking Lot walkway, and extension of the walkway in front of the Metrology Building.
Ohio-Native Meadow Project
UNDERWAY
Modeled after both the Horton Building Plaza project inspired by Dawes Arboretum and a Ohio prairie project at The Wilds, the Port Authority has begun a project to reclaim a one-acre area north of Building 4 as a meadow using Ohio-native plants. Showcase Landscaping will be thatching the area in November and the Port Authority will be planting an Ohio-native wildflower and prarie mix. The project is a test of this approach to grounds maintenance. The plan also includes benches and maintained recreational areas within the meadow.
Monument Sign Project
UNDERWAY
Construction of a monument sign identifying Goodrich as a tenant in the Horton Building is under construction. The sign is being constructed by Claggett and Sons.
Pavement Repairs
COMPLETE
Minor pavement repairs around the campus in the Fall of 2011 were completed in early November.
Fire Pump Relocation
UNDERWAY
Layton Inc, was awarded the contract to update and relocate the fire pump servicing Building 4. The project, designed by DLZ is expected to save over 1.5 million gallons of fresh water per year. The new fire pump will be located in south west corner of Building 4.
Waterline Consolidation
UNDERWAY
This project provides for consolidation of water lines on the west side of the campus. Layton, Inc. will be making changes to underground water lines during the first quarter of 2012, as a result of the new City water tower and the Boeing fire pump relocation.
See the archive of projects completed in 2011.
Also see the archives of Base campus projects from 2010 and previous years back to 2002.
Make An Inquiry to The Facilities Manager